MPSC PYQAptitudeenglish

Work done by Arun in one day is half of the work done by Sachin in one day. Work done by Sachin in one day is half of the work done by Rahul in one day. If Rahul alone can complete the work in 14 days, in how many days can Arun, Sachin and Rahul together complete the work?

A.4
B.6
C.8
D.5

Correct answer: C

Source paper

MPSC Group C Combined Pre 2024 (English)